Job Instruction Breakdown Sheets Help Design Workcell Training

Another Job Instruction Session is almost in the can this week...

Job Breakdown Sheets help us see work in new ways. The example this week is in a workcell and with the team leader of that workcell. She wrote one job breakdown sheet for the entire job about (40 steps) in the workcell. Naturally, she had many questions:

1) "This sheet feels like it is too long, with too many steps, so we are not using this the way I think we should."

A JBS should be about 5-7 steps and no more than 10 if you can help it. Why? That's about all one person can retain in their memory. The problem she discovered was that many thought the JBS should be used as a reference. So, the natural inclination was to put it all in one sheet so it was seen as, "the book". The result is that no one really used it effectively. Bottom Line: Use the JI-KISS principle: Keep It Short & Simple.

2) "I know that breakdown sheets should be short, but I don't see anyway to break this job down any further."

To the genba we go! A further analysis of her 40 step job found logical stopping points in the job. This helped the team leader see where she could break the job down from one job into six tasks, two of them important quality checks. Doing this will help her achieve several goals that she has been struggling to meet:

Emphasizing quality checks. Breaking the quality checks out separately will help emphasize the key points of the job.

Meeting production goals. Currently, she does a lot of follow-up when training people because the training process is so lengthy - due to the one, 40 step JBS. By breaking it into six parts, she can train a person in one part and monitor the person in the workcell while working on the other five parts. Her plan will be to stagger the training throughout the day, and this is easier for her to do if the job is in smaller, digestible chunks. Bottom Line: the trainee is trained on the job, the team lead maintains a reasonable production level vs. zero, and she can monitor the trainee at the same time.

3) "We have loaded up the JBS with pictures. Should we have done that?"

Visual training aids are great. Pictures do speak a thousand words. Still, I hesitate to load up the pictures in a JBS for several reasons and only do so as a last resort:

Pictures often need updating. Products, materials, methods and tools will change as kaizen continues. Pictures need to be updated accordingly. This makes the cost of training go up and the delays of effective training increase. And if the JBS isn't updated immediately, the credibility of management support functions diminishes. Worse yet, the trainer is more inclined to NOT use the JBS because it is not up-to-date: "that isn't right anyway, so I'll just wing it."

Physical or Visual Aids in the Workplace are Better. If you are showing somebody how to route a flexible cable circuit through a molded assembly, nothing beats a physical model of the work itself. Make up a sample and keep it at the point of use. Your training aid is always up-to-date this way because the worker can create a new sample as needed. Picture maintenance is no longer required. This helps us also understand why the best JBS are usually written in pencil: the leaders in the area change it immediately to reflect the best standardized workplace practice.

Pictures work BEST when there is no other way to train. Sometimes a picture on the JBS is necessary. Perhaps you need a diagram of an assembly. Or perhaps a keypoint is related to something that can not be seen in the workplace, so a picture helps you describe the keypoint better. In a past life, a technician used x-rays of welded assemblies (he kept them from inspections) to show me how certain structures we designed were made. In this case the picture helped him do a better job of training.

The key point here is this:

The JBS is an aid FOR the trainer, it is NOT meant to replace her.

If your intent is to have documents replace your trainers, then you do not need Job Instruction Training, you need technical writers and illustrators.

Hopefully these tips help you like they are helping this team leader.
Read more »»  

Auto Bailouts - GM Facts and Fiction??

Here is a website of great interest to millions of people - right now. There are a lot of problems with the U.S. auto industry...there is not one single solution or one single problem we can point a finger at. I'm not sure if this website helps or hurts as we try to grasp the situation.

The problem I have with the bailout is that ultimately, we are just injecting some cash into a business that may or may not be used for growth and we may or may not see any of it returned to us taxpayers. It just isn't clear what will happen with that $25 billion. The Big Question I have for the Big Government regarding the Big Three is, will this bailout PREVENT an auto industry crash - helping us rightfully avoid the catastrophe promised if they do fail? My feeling is that if the Big Three fail it is of their own doing - is this something the government can prevent without screwing it up in the future? I suppose that there are some protectionist measures that could occur, but that will most likely result in increased costs for consumers...

As taxpayers then, shouldn't we be calling for the government to create manufacturing incentives for the creation of new domestic car companies with this bailout, which is going to happen with our without our consent? Not to be too pessimistic, but do we expect the Big 3 to change the overhead structure of their health care and pension legacy costs, union relations, supply chain and purchasing practices anytime soon? A lot has to happen to be competitive with cash-flush Toyota and others.

The only thing that is going to change the Big 3 is the Big 3 themselves. Economic conditions, tax incentives, government policy and consumers will change - but whether or not the Big 3 anticipate problems and proactively adapt to these changes is ultimately up to them, is it not?
Read more »»  

Microsoft Office 2007 Command Converter - Heaping Waste

In the spirit of the ever lengthening Halloween-Thanksgiving-Christmas-Holiday season, I would like to spread a little joy around...

And what a joy it is in learning a practically brand new interface in Office 2007 just so I can get the same results obtained in 2003! The new ribbon menu does have a new, certain flavor to it, I think I detect a dash of "throw-my-laptop-out-the-window" in there.

If you are going through the conversion from Office 2003 to 2007, it's like a Lean journey, its endless. Except in this journey their is no pursuit of perfection. Instead, you are embarking on an endless journey for your favorite 2003 commands that have simply vanished, because someone had a great idea that 300 million icons needed a facelift.

Thankfully, Microsoft has sort of redeemed themselves, well o.k., not really. But they are trying by heaping some more waste on top of the 2007 cesspool. Follow this link to a Flash converter for your 2003 commands. When you click on the commands, the screen instantly switches over to a Flash animation of where that same command is in 2007. You won't recognize your long lost friends in the new 2007 neighborhood, but you sure will be glad you found them!

THANKS, Microsoft, for adding another whole layer of work to this infuriating suite!
Read more »»  

It's a Waste Free Christmas Season, Charlie Brown!

I love Christmas. And since Halloween is over, the Christmas season has unofficially begun. (I heard the all Christmas song radio station this weekend.) AAAAGGGHHH!

There is a lot of inherent waste when its comes to Christmas. Return gifts in the subsequent days after the big day come to mind. With all that said, I don't have any strong feelings about some of the silly things that go along with the season - (like playing Silent Night 480,000 times in two months.)


There are two things that come to mind though and they aren't really Christmas' fault so we can rail on them for a moment:


1) The inevitable and annual Stepping on a Lego in the Middle of the Night event,


2) Packaging! You know what I mean. All of the joy in gift giving results in 15 trash bags of cheap cardboard nobody will recycle, enough blister packs to mold a new trunk lid for a Saturn Vue, 1,500 "anti-theft" steel twisty ties, several lacerations and one missing tooth!!!


Amazon has recognized consumers "wrap rage" is launching some new waste-free-packaging products through their "Frustration-Free" products. Check it out. When its time to open presents, you can skip the need for wire cutters, blowtorches, safety goggles and band-aids this year. Plus you can do your part to reduce landfill waste.




There are customer pictures and videos of gift opening mishaps at this site as well, and you can even upload your own.

Read more »»  

Standardizing Waste using 5S

I've railed on mainstream 5S programs for quite sometime now. Thanks for enduring this. The latest travesty was the 5S article in the Wall Street Journal. A lot of companies are making a good go of 5S and visualizing their workplaces, indicating that some folks are taking the genba kaizen to the next level.

The following example though illustrates how we still get caught up in doing 5S without really thinking about WASTE FREE standardization. Take a simple thing found in the the genba - a machine gauge.

Look at the following picture. The gauges do the same thing on different machines. The genba people did a GREAT job of visualizing the ranges on each gauge. But what is the problem here? What questions do you have? Is this waste free standardization? How hard would it be to train someone if many things in the workplace are in a similar non-standardized condition? Which one is correct? Is one process making better product then the other? Is this truly a stable process?



5S is NOT housekeeping. The area this picture was taken was very clean and well kept. So this group had moved beyond the basic cleaning level of 5S: this picture illustrates that the genba people were really thinking about how to make their job easier by knowing the condition of the machine. Cleaning is the basic easy level of 5S, this visualization is another level up. But when our standardization is not waste free, we will have a problem moving beyond the 3S level.

So, the next question our leaders have to ask these people FIRST: is this gauge reading important to the quality of the operation? If not, don't mark it, it so then we have more questions to ask. What is the failure point if the system isn't operating within range? What should the operation range be? How does this affect the operation? Is it in the correct range now? What should you do if it runs out of range?

So many questions that go beyond visualization, yet the visual factory should answer these questions for us.